In what context is an agile analyst working when they recommend stopping funding for an initiative that has delivered its promised value?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the IIBA Agile Analysis Certification Test with our comprehensive quizzes. Use flashcards and multiple choice questions with hints and explanations to enhance your learning and exam preparation!

The correct choice highlights the importance of strategic decision-making within the agile framework. When an agile analyst recommends stopping funding for an initiative that has already delivered its promised value, they are operating within the Strategy Horizon. This horizon focuses on long-term goals and overall alignment with organizational strategy.

In this context, the decision to cease funding is based on the evaluation of whether the initiative continues to deliver value in alignment with the strategic objectives of the organization. If an initiative has reached its goal and there’s no further strategic benefit to continue investment, it becomes a prudent choice to reallocate resources to other initiatives that may provide greater value or align more closely with evolving strategic priorities.

The other options do not quite fit this scenario. The Delivery Horizon deals more with the actual execution and delivery of products, not the strategic assessments of value over time. The Initiative Horizon specifically focuses on the lifecycle of individual projects, whereas the Strategy Horizon encompasses a broader view of how initiatives contribute to the overall mission and vision of the organization. Thus, the recommendation to stop funding aligns best with the strategic oversight needed in decision-making at that higher organizational level.