What action should an analyst take if a delivery team cannot complete a User Story due to dependencies that were overlooked?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the IIBA Agile Analysis Certification Test with our comprehensive quizzes. Use flashcards and multiple choice questions with hints and explanations to enhance your learning and exam preparation!

The best course of action for an analyst in this scenario is to work to identify why the dependency was missed and apply the learning to avoid the issue in the future. This approach emphasizes the importance of continuous improvement within Agile practices. By analyzing the situation and understanding the root cause of the oversight, the team can develop strategies to enhance their processes and prevent similar issues from recurring.

Identifying the reasons behind the missed dependency fosters a culture of transparency and learning, which is essential for any Agile team. It supports the idea that the team should collectively learn from experiences, enabling them to adapt and evolve over time. This proactive stance is fundamental in Agile methodologies, where the focus is not just on delivering features but also on improving team dynamics and operational processes.

While discussing the issue in the Retrospective is also valuable, it can be a part of the broader action of identifying why the dependency was missed and serves as a reflection rather than a proactive step to prevent future occurrences. Conducting a Spike may provide insights or exploration, but it doesn’t directly resolve the underlying issue of the missed dependencies. Facilitating a Value Stream Mapping workshop, on the other hand, concentrates on mapping processes rather than specifically addressing the missed dependencies in the context provided. Thus, the choice of